As of 11/4//2015, SRS has removed 1700 of the 5718 cubic yards of sediment. They should be finishing up with the north shore area (Site#3) the second or third week of November. They will then begin to work on sites #1 & #2, with the goal to complete those areas by the end of December, weather permitting. The north side (site #3) was done first because they can break through ice in the channels much easier if necessary.
Stay Tuned!!!